CS 26.331 Compliance plan for STC holders
CAA ORS9 Decision No. 1
Compliance with point 26.331 of UK Part-26 is demonstrated when a compliance plan exists that includes:
(a) a project schedule identifying all the major milestones for meeting the compliance times specified in points 26.332 to 26.334 of UK Part-26;
(b) an explanation of how the changes that affect the FCS will be identified and presented;
(c) a proposed means of compliance with the DTE required by points 26.333 and 26.334 of UK Part26;
(d) a plan for submitting drafts of all the compliance items required by point 26.330 of UK Part-26 for review by CAA not less than 60 days before the applicable compliance date.