GM 21.A.126(a)(2) Production inspection system – Identification of incoming materials and parts
CAA ORS9 Decision No. 1
All parts and materials coming from external parties should be identified and inspected to ascertain that they have not been damaged during transport or unpacking, that the incoming parts and materials have the appropriate and correct accompanying documentation and that the configuration and condition of the parts or materials is as laid down in that documentation.
Only on completion of these checks and of any incoming further verifications laid down in the procurement specification, may the part or material be accepted for warehousing and used in production.
This acceptance should be certified by an inspection statement.
A suitable recording system should allow reconstruction at any time of the history of every material or part.
The areas where the incoming checks are carried out and the materials or parts are stored pending completion of the checks should be physically segregated from other departments.