GM1 21.A.7(e) Completeness and timely availability of changes to the ICA (TC/RTC)
CAA ORS9 Decision No. 48
Point 21.A.7(e) regulates the distribution of changes to the ICA required from the TC/RTC holder. Those changes to the ICA could result from the design change process (minor and major changes), in-service experience, corrections, and others.
For a UK TC/RTC holder/applicant, a programme showing how changes to the ICA are distributed is part of the respective procedures (e.g. design organisation procedures, or alternative procedures used to demonstrate capabilities). For changes to the ICA triggered by design changes, typically these procedures follow the same principles as those available for TC/RTC, Options 1 to 3, while taking into account the relevant privileges, e.g. that a DOA may approve minor changes in accordance with point 21.A.263(c)(2).