GM1 SPO.OP.230 Standard operating procedures
CAA ORS9 Decision No. 1
TEMPLATE FORMS
Template Form A — Risk assessment (RA)
|
Date: RA of Responsible: |
|---|
|
Purpose: |
|
Type of operation and brief description: |
|
Participants, working group: |
|
Preconditions, assumptions and simplifications: |
|
Data used: |
|
Description of the analysis method: |
|
External context: |
|
• Regulatory requirements
• Approvals
• Environmental conditions (visibility, wind, turbulence, contrast, light, elevation, etc. unless evident from the SOPs)
• Stakeholders and their potential interest |
|
Internal context: |
|
• Type(s) of aircraft
• Personnel and qualifications
• Combination/similarity with other operations/SOPs
• Other RA used/considered/plugged in |
|
Existing barriers and emergency preparedness: |
|
Monitoring and follow up: |
|
Description of the risk: |
|
Risk evaluation: |
|
Conclusions: |
Template Form B — Hazard identification (HI)
Date: ………………………………..HI of …………………………… Responsible: ………………………………………………
|
Phase of operation |
Hazard ref |
Hazard |
Causes |
Existing controls |
Controls ref |
Comments |
|---|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note:
Haz ref: A unique number for hazards, e.g. for use in a database Controls ref: A unique number for the existing controls
Template Form C — Mitigating measures
Date: ………………..................... RA of ……………………… Responsible: ………………………………………………
|
Phase of operation |
Haz ref |
Consequence |
Existing mitigation actions |
Mitigation ref |
L |
S |
Further mitigation required |
|---|---|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note:
Haz ref: A unique number for hazards, e.g. for use in a database Mitigation ref: A unique number for the mitigation actions
L: Likelihood
S: Severity
Template register A — risk register
|
Ref |
Operation/Procedure |
Ref |
Hazard |
Ref |
Consequences |
Mitigation actions |
L |
S |
Monitoring |
|---|---|---|---|---|---|---|---|---|---|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
|
Note:
L: Likelihood
S: Severity